Caulmert Limited were appointed on behalf of Viridor Waste Management Limited to provide a full design, management and supervision role for the development of a new waste materials handling facility (MRF).
The project involved the design and construction of a recycling storage building, car park, lorry park and external lighting. Our duties were taken from the initial concept and design stage through to contract completion. Caulmert prepared the civil and structural design and specifications for the works as well as preparing the contract documents (NEC 3rd Edition), the bills of quantities, drawings and specification.
Caulmert tendered the contract and also administered the contract through tender stage, tender assessment, contractor interviews, appointment on behalf of the client as well as site supervision and site health and safety audits.
The scheme was completed in February 2012 and within the clients programme and budget.